WIP Ready Journal

Field notes on construction finance.

Practical writing on WIP schedules, ASC 606, profit fade, and the monthly close — for the finance teams and project managers who actually build the numbers.

PM Playbook A single large question mark drawn as a financial schedule line, its dot a small solid ledger block, one teal accent.
WIP 101 A single measured column rising just past a horizontal threshold line, its overshoot marked in plum on warm off-white.
WIP 101

You Just Outgrew the Small-Contractor Tax Exemption. Here's Your First WIP Schedule.

Your three-year average gross receipts crossed the $32M IRC §460 line for 2026, so completed-contract is off the table and percentage-of-completion is now required. Here is the first WIP schedule you have to build, the columns it needs, and a first-month checklist.

WIP 101 Flat wall with a central gate opening; an upright document card stands in the gap as the pass, three markers facing it.
WIP 101

WIP Bid Prequalification: What GC Primes and Private Owners Check Before They Let You Bid

Your WIP schedule is not just a bonding document. GC primes and private owners require it before they let you bid, a separate gate from your surety, and public agencies often ask for the same work-on-hand detail. Here is what each committee reads.

Product Submission markers reach a cycle-close deadline gate; one lags behind in cobalt, keeping the WIP schedule from closing.
Product

Why Your PMs Don't Submit Their Cost-to-Complete on Time (And How to Fix It)

PMs don't skip their cost-to-complete out of laziness — they're avoiding a guess that can be read back to them later. Four reasons they submit late, and the specific fix for each, so your WIP closes on time.

WIP 101 A funnel narrows four input streams into one thin line feeding a calm financial schedule, the output stream in deep red.
WIP 101

Why Your PM's Cost-to-Complete Is Usually Wrong: Four Reasons That Distort Your WIP Report

The ETC is the one number on your WIP that comes entirely from a PM's judgment. Four construction-specific conditions make it systematically too low — and each one prints a gain on the schedule your surety reads as real.

WIP 101 Vertical spine of five monthly WIP-check nodes: three solid, two outlined in deep red, over faint month ticks on warm paper.
WIP 101

The Five WIP Signals a Construction Controller Should Track Every Month

You already build a WIP every month. These are the five numbers to pull from it each cycle — gain/fade velocity, overbilling coverage, ETC staleness, underbilling aging, and POC accuracy — and what each one predicts about where your jobs are heading.

WIP 101 A near-complete job's progress bar with one tall underbilling block still growing at its end, in a single deep-red accent.
WIP 101

The WIP Overbilling and Underbilling Patterns That Trigger a Surety Flag

Three billing patterns put your WIP on a surety underwriter's watch list: sustained overbilling, late-stage underbilling, and single-job concentration. Here's the named Old Republic carrier data on the underbilling case, the escalation sequence these patterns trigger, and how to correct the position in Procore before renewal.

PM Playbook Four method paths fan from one budget line to four different cost-at-completion totals, the chosen path marked in teal.
PM Playbook

Procore's Four Forecast-to-Complete Methods, Explained for the PM Who Has to Pick One

Procore gives you four ways to calculate Forecast to Complete. Here's which method to pick for each budget line — and what your choice does to how far along finance can say the job is.

Profit Fade A four-quarter line chart that rises, then bends into a steepening downward fade, the final segment in a muted teal accent.
Profit Fade

Job Gain and Job Fade in Your WIP: What the Trend Line Is Telling You

The gain/(fade) column is the period-over-period change in each job's estimated gross profit. Read its slope across three or four WIP cycles and it tells you where a job lands at 100% — while there's still runway to act.

WIP 101 A thick WIP report seen edge-on, small index tabs down its side, two tabs flipped up in a single muted accent color.
WIP 101

What Surety Underwriters Actually Look for in Your WIP Report (And the 5 Red Flags That Kill Capacity)

Surety underwriters read every WIP report for the same five patterns. Here's what each one signals about your file — and how to fix it before your renewal meeting.

WIP 101 A WIP schedule sheet with a finance loupe held over it, five quiet checkmark ticks down one margin in a single accent color.
WIP 101

How to Read Your WIP Report Like a Surety Underwriter (Before Your Annual Review)

Your surety runs the same five diagnostic tests on your WIP at every renewal. Here's how to run them yourself first — with the exact pass/fail threshold for each — 60 to 90 days before the meeting.

PM Playbook A folded jobsite estimate note resting on a faint financial schedule, the note marked in a single accent color.
PM Playbook

How to Update Your Cost to Complete in Procore

Procore has a Forecast to Complete column in the Budget tool — here's how to update it, which calculation method to pick, and why finance asks you for that number every month.

WIP 101 Four ascending construction-finance steps building left to right into one final result block, in cobalt and ink-navy.
WIP 101

How WIP Is Calculated in Construction (With a Worked Example)

The four-step formula chain every controller uses to build a WIP schedule — EAC, percent complete, earned revenue, and the over/under-billing position — with a full worked example and the adjusting journal entry.

WIP 101 A short stack of dated WIP schedule cards on a calendar grid, the most recent month raised forward.
WIP 101

What a Hardening Surety Market Means for Your WIP (2026)

Capacity is ample in 2026, but the bar to qualify for it just rose. Here's what a hardening surety market means for how often — and how clean — your WIP schedule needs to be.

ASC 606 A pie chart filling partway as a cost-to-complete estimate sets the slice, with a contract-value bar beside it.
ASC 606

Percentage-of-Completion Under ASC 606: A Contractor's Practical Guide

How contractors compute percentage-of-completion with the cost-to-cost method, why the PM's cost-to-complete drives the whole calculation, and what changes for tax versus GAAP.

PM Playbook Five stacked work blocks of different sizes feeding into a single bracket, one detached and floating.
PM Playbook

How Change Orders Move Your Cost to Complete

Every change order is a question about how much more it will cost to finish the job. Here's how each type — approved, pending, disputed, or deduct — moves the number you report.

WIP 101 A tall working-capital bar shrinking to a shorter adjusted bar as discounted asset slices lift away.
WIP 101

Working Capital and Bonding: The Number Sureties Care About Most

Sureties don't use your raw working capital figure to set your bonding limit — they adjust it. Here's what gets stripped out, the rule-of-thumb multiple, and how your WIP schedule feeds the number.

WIP 101 Two side-by-side construction ledger columns with offset totals lines, joined by one corrective bridge entry in indigo.
WIP 101

Why Your WIP Never Ties Out — and What to Do About It

Your WIP schedule and the general ledger never quite agree. Here are the four structural reasons a WIP fails to reconcile, and the exact adjustment journal entry that trues it up.

Product Three WIP tool types as panels: one nested inside a Procore frame, two floating outside as separate dashboards.
Product

WIP Software for Procore: What Actually Works Without Leaving Procore

Most WIP software for Procore makes you work somewhere else — an ERP, a BI dashboard, or a spreadsheet. Here is how the categories actually compare, and where the embedded option fits.

WIP 101 Construction cost-code ledger feeding a single percent-complete figure into a monthly WIP schedule sheet.
WIP 101

Construction Job Costing: How It Feeds Your WIP Schedule

Job costing tells you where each job is. The WIP schedule turns those cost codes into the earned-revenue, billing, and forecast picture your surety, bank, and CPA actually read.

WIP 101 Top-down view of an open construction WIP schedule with an embossed surety approval seal resting on its corner.
WIP 101

What Your Surety Underwriter Actually Reads in Your WIP Schedule

Your WIP schedule sets your bonding capacity. Here is the exact four-question read your surety underwriter runs — and how each column builds or destroys your limit.

Product Flat illustration of a six-station horizontal close pipeline ending in a finished WIP schedule, with one ochre stage marker.
Product

How to Run a Monthly WIP Close in Procore: 6 Steps

A step-by-step walkthrough of the six-step monthly WIP close — from the Procore data pull to the surety-ready export — and where the 45 minutes of active work actually goes.

ASC 606 Two-pan balance scale weighing billings against earned revenue on a construction WIP schedule, tilted to the billed side.
ASC 606

Over/Under Billing in Construction: Formula, Worked Example, and What It Tells Your Surety

Over/(under) billing equals billed to date minus earned revenue. The formula chain as a table, a worked example that recomputes exactly, and what each position tells your surety underwriter.

PM Playbook A construction project manager on a jobsite entering a cost-to-complete number on a phone.
PM Playbook

What Is Estimate to Complete? A Guide for Project Managers

Estimate to complete is how much more it will cost to finish the job from today. A plain-English guide for the project manager who produces the number — and the two-minute monthly habit that protects it.

WIP 101 Flat illustration of a surety credit gauge tied by a thin line to a work-in-progress schedule beside a mid-rise jobsite.
WIP 101

How to Track and Increase Your Bonding Capacity from Live Financials

Your bonding capacity isn't a fixed credit line — it's a number your surety reads off your work-in-progress schedule, and it moves every month. Here's how to calculate it, track it from live Procore financials, and grow it.

ASC 606 Split diagram: a project manager's ETC entry feeding the EAC column on a construction WIP schedule.
ASC 606

EAC vs ETC on a Construction WIP Schedule

ETC is the project manager's estimate of the cost still required to finish a job; EAC equals costs to date plus ETC. On a construction WIP schedule that one number sets your percentage complete, earned revenue, and projected margin.

WIP 101 An Excel WIP schedule beside a phone, marking where a spreadsheet stops scaling for a busy general contractor.
WIP 101

Free Construction WIP Schedule Template (Excel) — and When to Stop Using It

A free Excel WIP schedule template with all 11 ASC 606 columns, formulas pre-wired, and a worked example — plus the honest checklist for when to stop maintaining a spreadsheet and pull the same columns from Procore instead.

WIP 101 A construction work-in-progress schedule with earned, billed, and over/under columns
WIP 101

What Is a WIP Schedule? The Construction Finance Guide (2026)

A WIP schedule is the monthly financial statement your surety, bank, and CPA use to judge every active job, comparing earned versus billed and the margin you will land at completion. Here are the columns, the formulas, and how general contractors actually produce one from Procore.

Profit Fade A gross-margin line fading from healthy to thin across a project timeline
Profit Fade

Profit Fade in Construction: How to Catch It Before Close (Not at Year-End)

Profit fade is your projected job margin shrinking as estimated costs climb. It hides until year-end because most teams rebuild the WIP too rarely. Here is how a controller catches it monthly, while there is still margin left to protect.

Product Procore project financials screen alongside a finished WIP schedule
Product

Can Procore Generate a WIP Report? Native Limits and the Faster Way

Procore holds the budget data but has no native WIP schedule. Forecast to Complete is not a surety-grade ETC. Here is exactly what Procore does, where it stops, and how to produce a bonding-ready WIP in about 45 minutes.

Monthly, like your close

One email a month. No fluff, just the numbers.

WIP technique, ASC 606 changes, and product updates — written for finance and field. Unsubscribe any time.

No spam · ~1 email / month · written for GC finance teams